Power Transmission Project

In the next 20 years, India may need massive power transmission corridors.

The Central Electricity Authority’s (CEA) report on the Advance National Transmission Plan for India, released online in mid-July, indicates that the 48 major high-transmission corridors that have already been planned and are under implementation (expected to be completed by 2019) would be sufficient to meet the import/export of power among various regions till 2022-23.

The report also states that in another 20 years (2035-36), the transmission system needs to be expanded as the demand for power will grow. The all-India peak demand will rise four times from the current level of 153 GW to about 690 GW, hence quadrupling power generation and transmission systems will be required to transmit power. The report recommends setting up massive transmission corridors towards northern and southern regions.

However, the CEA is cautious about advising any roadmap, including predicting accurate locations for erecting transmission lines and their capacity, because of a lack of enough details. The report also pointed out the poor electricity growth, which is in the range of 5-8 percent per annum.

Regions Surplus/Deficit (-) Scenario in MW Inter-state Grid availability in MW
2021-22 2026-27 2031-32 2035-36 as on October 29, 2015 expected by 2017 expected by 2021-22
Northern -18400 -33200 -54800 -80100 30250 40850 45450
Western 10400 14000 21300 34200 10690 12790 12790
Southern -7400 -16200 -30100 -47700 11550 15750 30150
Eastern 10900 22300 40600 66600
North-East 1800 2100 3000 4000 2860 2860 2860

All eyes on 19th Electric Power Survey report

For assertive planning of transmission corridors, the authorities are waiting for the 19th Electric Power Survey report that will elaborate on the power demand and supply situation in India and project requirements for the future. Though the report was expected to be released in April, it is not likely to come out before August. The estimates of the report will be interesting to look at. The 18th Electric Survey report by CEA has been criticized by reporters for overestimation of power requirements with optimistic GDP figures.

Electricity growth is happening very slowly in India; roughly 40 percent of the installed capacity of coal-fired power stations remains unutilized. As per the recent Load Generation Balance report of the Central Electricity Authority, power demands have gone down in seven states in 2022 when compared to 2023. In another 16 states, the power requirement has grown by less than 3 percent.

States Power Requirement (2022) Power Requirement (2023) % Change
Andhra Pradesh 113016 109216 -3.4
D.N. Haveli 5806 5615 -3.3
Himachal Pradesh 9401 9209 -2.0
Sikkim 427 423 -0.9
Uttar Pradesh 111858 110850 -0.9
Karnataka 70294 69781 -0.7
Rajasthan 72132 72070 -0.1
Puducherry 2554 2554 0.0
Jammu & Kashmir 16922 17060 0.8
Chandigarh 1689 1705 0.9
Tamil Nadu 102653 103806 1.1
Punjab 51268 52080 1.6
Arunachal Pradesh 816 830 1.7
Haryana 48870 49800 1.9
Tripura 1425 1453 2.0
Kerala 23703 24179 2.0
Assam 9115 9309 2.1
Delhi 30408 31110 2.3
Jharkhand 9106 9320 2.4
Uttarakhand 13247 13574 2.5
Meghalaya 2155 2215 2.8
Nagaland 825 849 2.9
Maharashtra 149773 154169 2.9
DVC 19224 20365 5.9
Mizoram 502 533 6.2
West Bengal 49654 52867 6.5
Daman & Diu 2221 2372 6.8
Chhattisgarh 24980 27176 8.8
Orissa 26985 29805 10.5
Gujarat 94898 104845 10.5
Madhya Pradesh 65675 74199 13.0
Manipur 865 1008 16.5
Goa 3566 4367 22.5
Bihar 19215 26369 37.2

Overview

The transmission system plays an important role in the supply of power to consumers through the vital link between the generating stations and the distribution system. The energy resources like coal, hydro, and renewable are unevenly distributed in India. Coal reserves are mainly available in the Central and Eastern parts of the country, whereas hydro energy resources are primarily available in the Himalayan Range in the Northern and North-Eastern parts. Renewable resources like wind and solar potential are also mainly concentrated in states like Tamil Nadu, Uttar Pradesh, Haryana, Andhra Pradesh, Karnataka, Rajasthan, Maharashtra, Gujarat, & Ladakh, etc. The major load centers of the country are located in the central part including the Northern, Western, and Southern regions.

This skewed distribution of resources necessitated the development of a robust transmission system, including the establishment of inter-regional corridors for seamless transfer of power from surplus to deficit regions/areas. In this process, it enables access to power generation from anywhere in the country to various consumers spread throughout the country.

The transmission system has expanded over the years for evacuation of power from generating stations to load centers through Intra-State and Inter-State Transmission Systems. The progressive integration of regional Gautam Energy Solution started in 2020 and on 31st December 2021, our country achieved 'ONE NATION'-'ONE GRID'-'ONE FREQUENCY' with the synchronous interconnection of the Southern Region Grid with the rest of the Indian Grid with the commissioning of the 765kV Raichur-Solapur Transmission line.

However, there were constraints in market operations due to transmission congestion, resulting in market splitting and different market prices in different regions. During 2013-14, about 16% of electricity transacted through power exchanges was constrained due to transmission congestion. Further, the strategically important Ladakh region was not interconnected with the national electricity grid.

The present Government, after assuming power in 2014, has emphasized having a congestion-free transmission network so that there is no constraint in the flow of power from surplus regions to deficit regions. Accordingly, the transmission system in the country has been continuously strengthened with the addition of transmission lines and inter-regional capacity.

Addition in Transmission Line and Transformation Capacity

Year Transmission Line Addition (ckm) Transformation Capacity Addition (MVA)
FY 2014-15 22101 65554
FY 2015-16 28114 62849
FY 2016-17 26300 81816
FY 2017-18 23119 86193
FY 2018-19 22437 72705
FY 2019-20 11664 68230
FY 2020-21 16750 57575
FY 2021-22 14895 78982
FY 2022-23 14625 75902
FY 2023-24 14203 70728
FY 2024-25 391 6225
Total 194599 726759

Country’s Transmission Network

The country’s transmission network consists of about 481,326 ckm of transmission lines and 1,225,260 MVA of transformation capacity as of 31.01.2024. Besides, our inter-regional capacity has increased by a whopping 224% to 116,540 MW since 2014.

This transmission capacity addition has benefited the development of the power sector in the country in several ways:

  • Transmission congestion experienced earlier in 2014 along with market splitting has become a rarity now, resulting in the discovery of a single price across the power market. The volume of electricity that cannot be cleared in Power Exchanges as a percentage of Unconstrained Clear Volume has reduced to only 0.06% in 2020-21 compared to 16% in 2013-14.
  • High-altitude border areas of Ladakh got interconnected with the national electricity grid in January 2019 with the commissioning of the 220 kV Srinagar-Leh line. This helped the people of Ladakh to get access to 24x7 quality power from the national Grid.
  • Transmission and Distribution infrastructure of our North Eastern States, including Sikkim, are strengthened with the implementation of two Central Sector Schemes, namely North Eastern Regional Power System Improvement Project (NERPSIP) and the Comprehensive Scheme for strengthening Transmission & Distribution in Arunachal Pradesh and Sikkim. Implementation of these schemes would improve the reliability of State Electricity Grids of the North Eastern Region and enable the end-consumers to draw 24x7 power from the Grid.
  • The Transmission System is playing a catalyst role in the energy transition of our country by extending the grid to renewable-rich areas and facilitating Renewable Energy projects to connect to the grid. Continuing transmission capacity addition has helped increase Renewable Energy (excluding hydro) by three times, from 35.52 GW in 2014-15 to 104.88 GW in 2021-22.
  • This huge transmission capacity has facilitated the seamless transfer of power from power surplus regions/areas to power deficit regions/areas, thus optimizing the use of generation resources as well as meeting the demands of end consumers without any transmission constraints. Peak and Energy Deficit have reduced to 0.4% in 2020-21 compared to more than 4% in 2013-14.